Long-Term Closures – Michigan Interchange

View the public notice for more information

Date/Duration

Road

Location

Details/Detour

Starting October 21, 2019

Springwells Street road bridge

Detroit

Once bridges at Springwells, Livernois and Clark are closed, adjacent bridges will remain open to allow traffic to cross  I-75 in both directions. They are (west to east): Green Street, Waterman Street, Dragoon Street, Junction Avenue, and  West Grand Boulevard.

Starting October 21, 2019

Livernois Avenue road bridge

Detroit

Once bridges at Springwells, Livernois and Clark are closed, adjacent bridges will remain open to allow traffic to cross  I-75 in both directions. They are (west to east): Green Street, Waterman Street, Dragoon Street, Junction Avenue, and  West Grand Boulevard.

Starting October 21, 2019

Clark Street road bridge

Detroit

Once bridges at Springwells, Livernois and Clark are closed, adjacent bridges will remain open to allow traffic to cross  I-75 in both directions. They are (west to east): Green Street, Waterman Street, Dragoon Street, Junction Avenue, and  West Grand Boulevard.

We appreciate your cooperation throughout this project. Every effort will be made to reduce inconvenience to drivers, residents and the business community. View the public notice for more information

The Michigan Interchange activities will be delivered in four phases.

 

Phase 1 – Starting October 21, 2019 and ending in fall 2020

  • The Springwells Street, Livernois Avenue and Clark Street road bridges, and the Solvay Street pedestrian bridge crossing I-75, will be removed and rebuilt. Information on traffic detours, road closures and detailed map of the construction areas can be found at our Detours and road closures.
  • The I-75 shoulder will be widened near the road bridges.
  • Construction of the connecting ramps, including pier construction along the I-75 median for the ramps will begin.
  • Reconstruction of I-75 between approximately 1,200 feet west of Springwells Street to Green Street.

    Phase 2 – Scheduled to begin in winter 2020 and end in spring 2022
  • The Green Street road bridge and the Beard Street pedestrian bridge crossing I-75, will be removed and rebuilt.
  • Reconstruction of I-75 West Fisher Service drives (northbound and southbound) between Green Street and Livernois Avenue.
  • Construction of ramps connecting I-75 with the US POE will continue.

    Phase 3 – Scheduled to begin in spring 2021 and end in winter 2022
  • The I-75 northbound West Fisher Service Drive and the I-75 shoulders will be rebuilt between Green Street and Livernois Avenue.
  • The I-75 southbound West Fisher Service Drive will be rebuilt from Junction Street to Livernois Avenue.
  • The southbound I-75 onramp at Clark Street, northbound I-75 onramp from Livernois Avenue, and northbound I-75 offramp to Campbell Street will be completed during this phase.

    Phase 4 – Scheduled to start in winter 2022 and end in winter 2023
  • Reconstruction of Fort Street, Jefferson Avenue, and Clark Street.
  • The northbound I-75 exit ramp at Clark Street and the southbound entrance ramp from Clark Street will be removed.
  • Work on the I-75 West Fisher Service drives will be completed between Junction Street and Clark Street.
  • The I-75 will be widened in the area of the I-75 northbound and southbound exit ramps at Clark Street.


    Information on traffic detours, road closures and detailed maps of the construction areas can be found at our detours and road closures.

     
New information from Gordie Howe International Bridge project team
View this email in your browser
 

 

We have a few project updates to share:

Upcoming Public Consultation Meeting

As part of the Gordie Howe International Bridge project, an 85-100’ wide landscaped perimeter is part of the US Port of Entry (POE) site design. This green space will provide public benefit with native pollinator- positive plantings, and a public multi-use path that will connect Campbell and Green Streets by running along the US POE Wall parallel to Jefferson Avenue. The Jefferson Wall is an opaque, 8’ high, non- climbable security wall that will have an aesthetic treatment on the public side facing Jefferson Avenue. It will reflect design cues, colors, and materials from nearby historic Fort Wayne. Three wall design alternatives have been presented by Bridging North America and are open for input from the US community until October 31, 2019.
 
Join us at a Public Consultation Meeting at the WDBA Southwest Detroit Community Office on October 29, 2019, from 4:00 p.m. - 7:00 p.m. to learn more about the options and vote on your favourite US Port of Entry barrier wall design. The meeting is open-house format. Read the public notice or vote online
 
PUBLIC CONSULTATION MEETING
Tuesday, October 29, 2019 WDBA Southwest Detroit Community Office 7744 W. Vernor Highway, Detroit, MI 4:00 p.m. – 7:00 p.m.​
 
Reminder - Michigan Interchange Bridge Closures
On October 21, 2019, Bridging North America began implementing long-term closures at three I-75 road bridges: Springwells Street, Livernois Avenue, and Clark Street in preparation for upcoming bridge demolition and reconstruction. The following road bridges will remain open for the duration of this work: Green Street, Waterman Street, Dragoon Street, Junction Avenue and West Grand Boulevard. For more information including detour routes and maps, click here.
 
 
 

Gordie Howe International Bridge Team