Long-Term Closures – Michigan Interchange
View the public notice for more information
Date/Duration |
Road |
Location |
Details/Detour |
Starting October 21, 2019 |
Springwells Street road bridge |
Detroit |
Once bridges at Springwells, Livernois and Clark are closed, adjacent bridges will remain open to allow traffic to cross I-75 in both directions. They are (west to east): Green Street, Waterman Street, Dragoon Street, Junction Avenue, and West Grand Boulevard. |
Starting October 21, 2019 |
Livernois Avenue road bridge |
Detroit |
Once bridges at Springwells, Livernois and Clark are closed, adjacent bridges will remain open to allow traffic to cross I-75 in both directions. They are (west to east): Green Street, Waterman Street, Dragoon Street, Junction Avenue, and West Grand Boulevard. |
Starting October 21, 2019 |
Clark Street road bridge |
Detroit |
Once bridges at Springwells, Livernois and Clark are closed, adjacent bridges will remain open to allow traffic to cross I-75 in both directions. They are (west to east): Green Street, Waterman Street, Dragoon Street, Junction Avenue, and West Grand Boulevard. |
We appreciate your cooperation throughout this project. Every effort will be made to reduce inconvenience to drivers, residents and the business community. View the public notice for more information
The Michigan Interchange activities will be delivered in four phases.
Phase 1 – Starting October 21, 2019 and ending in fall 2020
- The Springwells Street, Livernois Avenue and Clark Street road bridges, and the Solvay Street pedestrian bridge crossing I-75, will be removed and rebuilt. Information on traffic detours, road closures and detailed map of the construction areas can be found at our Detours and road closures.
- The I-75 shoulder will be widened near the road bridges.
- Construction of the connecting ramps, including pier construction along the I-75 median for the ramps will begin.
- Reconstruction of I-75 between approximately 1,200 feet west of Springwells Street to Green Street.
Phase 2 – Scheduled to begin in winter 2020 and end in spring 2022
- The Green Street road bridge and the Beard Street pedestrian bridge crossing I-75, will be removed and rebuilt.
- Reconstruction of I-75 West Fisher Service drives (northbound and southbound) between Green Street and Livernois Avenue.
- Construction of ramps connecting I-75 with the US POE will continue.
Phase 3 – Scheduled to begin in spring 2021 and end in winter 2022
- The I-75 northbound West Fisher Service Drive and the I-75 shoulders will be rebuilt between Green Street and Livernois Avenue.
- The I-75 southbound West Fisher Service Drive will be rebuilt from Junction Street to Livernois Avenue.
- The southbound I-75 onramp at Clark Street, northbound I-75 onramp from Livernois Avenue, and northbound I-75 offramp to Campbell Street will be completed during this phase.
Phase 4 – Scheduled to start in winter 2022 and end in winter 2023
- Reconstruction of Fort Street, Jefferson Avenue, and Clark Street.
- The northbound I-75 exit ramp at Clark Street and the southbound entrance ramp from Clark Street will be removed.
- Work on the I-75 West Fisher Service drives will be completed between Junction Street and Clark Street.
- The I-75 will be widened in the area of the I-75 northbound and southbound exit ramps at Clark Street.
Information on traffic detours, road closures and detailed maps of the construction areas can be found at our detours and road closures.
|